Runcorn_14_full

Runcorn Boiler Plant Project

Location: Runcorn, England
Client: Alstom Power Limited
Value: £1,340,000
Construction Period: 9 Months
Year Completed: 2005

Installation of electrical switchgear and equipment and installation of instrumentation and electrical systems associated with three boiler units and a water treatment plant. Much of the work undertaken is in live operational environments and requires hazardous area equipment training.