Location: Cumbria, England
Client: British Nuclear Fuels plc
Value: £33,561,000
Construction Period: 52 Months
Year Completed: 1993
Enabling works associated with new electrical distribution system for Dungeness ‘A’ Power Station.
The scope of work includes detailed design, installation of a free issue transformer, switchboard and package sub-stations, civil construction of necessary foundations for new equipment, installation of cable tray and associated steelworks and supply of 6.6kV cables.