Location: Ayrshire, Scotland
Client: Scottish & Southern Energy
Construction Period: 10 Months
Year Completed: 2005
Hadyard Hill Wind Farm 132/33kV substation project works include the establishment of two new outdoor open terminal substations, including the provision of switchgear, civil works, control and protection, AC and DC systems and ancillary equipment.
Cruickshanks work consists of project management, design, manufacture, installation and commissioning.