Location: Eccles, England
Client: SP Power Systems Limited
Value: £1,200,000
Construction Period: 20 Months
Year Completed: 2004
The project includes the establishment of 9 bays of 132kV outdoor open terminal switchgear including the provision of control and protection equipment, AC and DC systems and ancillary equipment, the contract also includes the replacement of control and protection equipment at a number of remote end substations.
Cruickshanks work consists of project management design, manufacture, testing, delivery and site commissioning of three substations control systems.